Scope of Works
MES Contractors delivered a complex, high-specification electrical installation to support critical control centre operations while managing the constraints of a live building and tight programme.
Critical Power & Backup Systems
- Full design and installation of standby generator with 20kl fuel tanks in basement
- Installation of UPS systems to ensure continuous power to 5th floor control centre
- LV panelboards and supporting electrical infrastructure designed and installed for independent operation
Renewable Energy Integration
- Design and installation of photovoltaic (PV) system to support building sustainability targets
- Integration with existing building MEP services, modified to accommodate independent electrical systems
Office Fit Out
- Full office electrical fit-out including new lighting, power distribution, and modifications to support operational requirements
- Coordination of works alongside live building operations to maintain safety and minimise disruption
Key Challenges & Delivery
Tight Programme
- Project completed in just four months, requiring careful planning and proactive project management
Bespoke Generator Modification
- Off-the-shelf generator adapted to meet bespoke requirements for critical control systems
Live Building Works
- Works carried out in a live council building, with strict safety and access protocols
- Coordination with trusted supply chain partners, including PipeFlex, for generator and diesel pipe installations
Outcome
MES Contractors successfully delivered a reliable, compliant, and future-proof electrical installation for the London Ambulance 111 Control Centre. Our expertise as trusted public sector electrical contractors ensured uninterrupted critical operations, high-quality office environments, and seamless integration of backup power systems.